Manufacturing & Testing

The production and inspection equipment behind the part list.

Equipment

Production and test machinery

Hangzhou Wonen is equipped with the following advanced production and inspection equipment.

数控绕线机(奥士玛 OZMA)

CNC coil winding machine

Winds the induction coil of magnetic sensors to a controlled turn count and resistance.

注塑成型机

Injection moulding machine

Moulds sensor housings, connector bodies and seals; vertical and horizontal machines in the shops.

信号检测仪与影像测量台

Signal detector

Verifies the output pulse of finished sensors against the reference waveform.

ABS 传感器自动检测机

ABS sensor parameter tester

Measures static resistance, output voltage per Hz and voltage ratio in one fixture.

High / low temperature chamber

Confirms the −40 °C to +125 °C operating range.

Salt-spray test chamber

Checks corrosion resistance of brackets, poles and terminals.

推拉力测试台

Pull-off (tensile) tester

Validates crimp and cable retention force.

Air-tightness tester

Verifies sealing of the housing and grommet.

慢走丝线切割机床

Wire-cut EDM & CNC

Mould electrodes and precision tooling components, made at our own tooling bases.

Process

From coil to packed part

Seven stages, all inside our own or long-standing partner sites — every step is traceable to a machine and an operator.

装配车间工位
  1. Design & tooling — mould and fixture design in house at the Yuyao and Wenzhou bases.

    Injection moulds, stamping dies and gauges.

  2. Metal processing — turning, stamping and machining of poles, brackets and rings at Wenzhou Jiate.

    Dimensions and surface finish sampled per batch.

  3. Coil winding — CNC winding, impregnation and resistance screening.

    Static resistance matched per vehicle, recorded part by part.

  4. Injection moulding — housing, connector and seal moulding.

    Vertical and horizontal presses running our own tooling.

  5. Assembly & parameter test — static resistance, output voltage, voltage ratio, tooth error.

    On the ABS parameter tester and signal detector.

  6. Environmental test — temperature cycling, salt spray, pull-off force, air-tightness.

    By batch and by type-test plan.

  7. Pack & ship — labelling against Wonen code and OE cross-reference, then despatch.

    HTE / VNB branded or neutral packing.

What we measure

Acceptance criteria from the requirement sheets

The values below are the technical requirements published for our two sensor families.

Magnetic-inductive

Passive
项目要求
1.1 工作温度−40 ~ +125 °C
1.2 静态电阻与车型匹配
1.3 输出电压10 ~ 40 mV/Hz
1.4 电压比值≤ 1.4
1.5 单齿误差≤ 2 %
1.6 12 齿以上累计误差≤ 7 %

Hall-effect

Active
项目要求
2.1 工作电压10 ~ 14 V
2.2 开启电流11.8 ~ 16.8 mA
2.3 关闭电流5.9 ~ 8.4 mA
2.4 上升时间26 µs
2.5 下降时间26 µs
2.6 占空比30 ~ 70 %
2.7 工作温度−40 ~ +125 °C

Measured records for a specific batch are available on request; type tests (temperature cycling, salt spray, pull-off, air-tightness) follow the agreed scope.